Dynamic payment breakdown
Enter total project price to auto-calculate installment amounts by milestone percentages.
Using total project price: PKR 14,850,000
Grey Structure Plan
Grey Structure Plan
Scope includes
- Excavation (Site Preparation)
- Underground Water Tank (UGWT)
- Overhead Water Tank (OHWT)
- Septic Tank with waterproofing treatment
- RCC structural works: foundations, beams, columns, slabs
- Brick masonry (internal & external)
- Internal and external plastering
- Electrical conduits and plumbing works
- Door frames (Chokhat) in coated metal
- Parapet wall and boundary wall construction
- Termite proofing (foundation level)
- Installation of electric motors and pumps
4 Marla: 3.5 months, 5 Marla: 4 months, 10 Marla: 6 months, 1 Kanal: 8 months (excluding Fridays, rain days and public holidays).
4-month post-completion rectification support. Variations or additional works are quoted separately in advance.
| Phase | Percentage | Amount (PKR) |
|---|---|---|
| Mobilization and advance | 35% | PKR 5,197,500 |
| Foundation / basement completion | 10% | PKR 1,485,000 |
| Ground floor RCC frame completion | 10% | PKR 1,485,000 |
| First floor RCC frame completion | 10% | PKR 1,485,000 |
| Mumty, parapet and boundary wall completion | 10% | PKR 1,485,000 |
| MEP internal work completion | 10% | PKR 1,485,000 |
| Indoor and outdoor plastering completion | 10% | PKR 1,485,000 |
| Final completion and handover | 5% | PKR 742,500 |